TIB Project Information

Town of Cusick's FY 2009 Overlay Project

2-E-888(002)-1

2-E-888(002)-1
FY 2009 Overlay Project

Multiple Locations

FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $95,770

County: Pend Oreille   |   Legislative District: 7   |   Project Length: 0.90   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 12/31/2010

Project Information

Lead Agency CUSICK
Funding Year 2009
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 5
Federal Route Number 9999
Project Length 0.90 mi.
ADT 250
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Robert Spencer
Contact Email cronrathm@msn.com
TIB Engineer Andrew Beagle
Last Payment Date 12/31/2010

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2007
Delayed Project Date 07/01/2010  
Predesign Approval
Design Approval 01/01/2008 04/16/2008
Bid Auth. Approval 01/01/2008 04/16/2008
Construction Approval 03/01/2009 04/30/2009
Project Closeout 10/31/2009 12/31/2009
Audit Date   12/31/2009
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 2,234
Construction Contract 96,758 88,196
Other Construction 0 5,340
Total Construction 96,758 95,770
     
Funding Surplus - 988  
Total TIB Funding 95,770 95,770

Local Funding Partners

Funding Amount Percent
CUSICK 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Prelevel and 1 inch overlay of River Road between Timber Street and the south city limits.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments