Town of Twisp's 2022 Overlay Award
2-E-886(006)-1
2-E-886(006)-1
2022 Overlay Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $441,984
County: Okanogan | Legislative District: 12 | Project Length: 0.49 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/16/2024
Project Information
Lead Agency | TWISP |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.49 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Andrew Denham |
Contact Email | publicworks@townoftwisp.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 01/16/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/20/2022 |
Bid Auth. Approval | 03/15/2023 | 05/25/2023 |
Construction Approval | 06/15/2023 | 06/29/2023 |
Project Closeout | 09/30/2023 | 01/11/2024 |
Audit Date | 01/16/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 43,279 | 48,087 |
Right of Way | 0 | 0 |
Total Design | 43,279 | 48,087 |
Construction Engineering | 43,279 | 46,859 |
Construction Contract | 288,552 | 396,144 |
Other Construction | 0 | 0 |
Total Construction | 331,831 | 443,003 |
Funding Increase | 66,874 | |
Total TIB Funding | 441,984 | 491,090 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
TWISP | 49,106 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 49,106 | 10.0% |
Project Description
Pavement Repair and Overlay of the following segments 5th Avenue - Glover St to Bridge St Lincoln Street - 5th Ave to 3rd Ave 4th Avenue - Glover St to Lincoln St
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |