Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Twisp's FY 2014 Red Town Project

2-E-886(002)-1

2-E-886(002)-1
FY 2014 Red Town Project

Multiple Locations

FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $319,959

County: Okanogan   |   Legislative District: 12   |   Project Length: 0.18   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 12/01/2014

Project Information

Lead Agency TWISP
Funding Year 2014
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.18 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Howard Moss
Contact Email publicworks@townoftwisp.com
TIB Engineer Andrew Beagle
Last Payment Date 12/01/2014

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2012
Delayed Project Date 07/01/2015  
Predesign Approval
Design Approval 01/01/2013 01/17/2013
Bid Auth. Approval 06/01/2013 07/26/2013
Construction Approval 08/15/2013 08/21/2013
Project Closeout 11/30/2014 11/13/2014
Audit Date   12/01/2014
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 20,000 41,247
Right of Way 0 0
Total Design 20,000 41,247
     
Construction Engineering 20,000 27,717
Construction Contract 210,000 250,995
Other Construction 0 0
Total Construction 230,000 278,712
     
Funding Increase 78,626  
Funding Surplus - 8,667  
Total TIB Funding 319,959 319,959

Local Funding Partners

Funding Amount Percent
TWISP 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project provides pavement repair, grinding and application of an overlay on streets within the central business district.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments