The streets are showing signs of distress. The current pavement condition ratings (PCR) for the segments are PCR Jonathan St - Western to Whitcomb (SR 97)59 Division St - Whitcomb (SR 97) to Tonasket56 Tonasket Ave - Division to 3rd50
Projects — TIB Project Information
TIB Project Information
City of Tonasket's FY 2020 Rehabilitation Project
2-E-885(003)-1
2-E-885(003)-1
FY 2020 Rehabilitation Project
Multiple Locations
FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $231,803
County: Okanogan | Legislative District: 7 | Project Length: 0.27 | TIB Engineer: Andrew Beagle | Last Payment Date: 02/16/2021
Project Information
Lead Agency | TONASKET |
Funding Year | 2020 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.27 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Alice Attwood |
Contact Email | tonasket@nvinet.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 02/16/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 02/25/2019 |
Bid Auth. Approval | 03/01/2020 | 04/30/2020 |
Construction Approval | 05/17/2020 | 07/24/2020 |
Project Closeout | 12/31/2020 | 01/29/2021 |
Audit Date | 02/16/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 41,014 | 41,312 |
Right of Way | 0 | 0 |
Total Design | 41,014 | 41,312 |
Construction Engineering | 41,014 | 24,591 |
Construction Contract | 227,858 | 165,900 |
Other Construction | 45,572 | 0 |
Total Construction | 314,444 | 190,491 |
Funding Increase | 757 | |
Funding Surplus | - 124,412 | |
Total TIB Funding | 231,803 | 231,803 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
TONASKET | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project provides full depth reclamation (FDR) and two-inch overlay of the approved segments.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |