Projects — TIB Project Information
TIB Project Information
City of Pateros's FY 2013 Seal Coat Project
2-E-883(003)-1
2-E-883(003)-1
FY 2013 Seal Coat Project
Multiple Locations
FY 2013 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $64,782
County: Okanogan | Legislative District: 12 | Project Length: 0.66 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/19/2012
Project Information
Lead Agency | PATEROS |
Funding Year | 2013 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.66 mi. |
ADT | 350 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Dale Parks |
Contact Email | paterospw@ncidata.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/19/2012 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2011 | |
Delayed Project Date | 07/01/2014 | |
Predesign Approval | ||
Design Approval | 01/01/2012 | 12/21/2011 |
Bid Auth. Approval | 05/01/2012 | 12/21/2011 |
Construction Approval | 06/01/2012 | 09/17/2012 |
Project Closeout | 10/31/2012 | 10/05/2012 |
Audit Date | 10/19/2012 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 3,500 | 0 |
Right of Way | 0 | 0 |
Total Design | 3,500 | 0 |
Construction Engineering | 3,500 | 448 |
Construction Contract | 64,000 | 64,334 |
Other Construction | 0 | 0 |
Total Construction | 67,500 | 64,782 |
Funding Increase | 448 | |
Funding Surplus | - 6,666 | |
Total TIB Funding | 64,782 | 64,782 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PATEROS | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project seals cracks, digs out & repairs alligatored areas and chips seals Lakeshore Drive, Commercial Avenue and Dawson Street.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |