The selected segments have pavement conditions ratings or received prep work that makes them suitable for chip seal as an effective treatment.
Projects — TIB Project Information
TIB Project Information
Town of Nespelem's 2009 WSDOT Chip Seal
2-E-880(002)-1
2-E-880(002)-1
2009 WSDOT Chip Seal
Town of Nespelem
FY 2010 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $65,043
County: Okanogan | Legislative District: 12 | Project Length: 1.58 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/20/2009
Project Information
Lead Agency | NESPELEM |
Funding Year | 2010 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 1.58 mi. |
ADT | 100 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Paul Mahre |
Contact Email | mahrep@wsdot.wa.gov |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/20/2009 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 10/24/2008 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | ||
Bid Auth. Approval | 10/24/2008 | 10/24/2008 |
Construction Approval | 01/01/2009 | 01/29/2009 |
Project Closeout | 09/30/2010 | 11/14/2011 |
Audit Date | 11/14/2011 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 95,000 | 64,380 |
Other Construction | 0 | 663 |
Total Construction | 95,000 | 65,043 |
Funding Surplus | - 29,957 | |
Total TIB Funding | 65,043 | 65,043 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NESPELEM | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project chip seals the following segments in conjunction with WSDOT North Central Region's 2009 Chip Seal on SR 155 10TH STG ST to C ST28 10TH STC ST to B ST24 5TH/B ST/4THC ST to A ST32 8TH STD ST to A ST36 9TH STG ST to B ST24 C ST10TH ST to 8TH ST63 C ST8TH ST to 5TH ST (E C/L)63 D STSR 155 to 8TH ST32 E STSR 155 to 10TH ST16 F STSR 155 to 9TH ST32 Prep work and pavement repair for the selected segments was completed under SCPP Project #2-E.880(001)-1 in 2008.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |