The existing surface of Elmer City Access Road shows deterioration with significant transverse cracking. The existing PCR is 56.
Projects — TIB Project Information
TIB Project Information
Town of Elmer City's FY 2018 Seal Coat Project
2-E-879(002)-1
2-E-879(002)-1
FY 2018 Seal Coat Project
Multiple Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $84,009
County: Okanogan | Legislative District: 12 | Project Length: 0.80 | TIB Engineer: Andrew Beagle | Last Payment Date: 03/16/2020
Project Information
Lead Agency | ELMER CITY |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 24AQ |
Project Length | 0.80 mi. |
ADT | 200 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Gary Benton |
Contact Email | elmercityclerk@live.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 03/16/2020 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 12/16/2016 |
Bid Auth. Approval | 01/01/2017 | 12/16/2016 |
Construction Approval | 06/01/2019 | 07/30/2019 |
Project Closeout | 03/01/2020 | 02/24/2020 |
Audit Date | 03/16/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 12,704 | 5,900 |
Right of Way | 0 | 0 |
Total Design | 12,704 | 5,900 |
Construction Engineering | 0 | 5,900 |
Construction Contract | 70,000 | 72,209 |
Other Construction | 0 | 0 |
Total Construction | 70,000 | 78,109 |
Funding Increase | 16,463 | |
Funding Surplus | - 15,158 | |
Total TIB Funding | 84,009 | 84,009 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ELMER CITY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project seals cracks, repair pavement and chip seals the surface of Elmer City Access Road from south to north town limit.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |