Projects — TIB Project Information
TIB Project Information
Town of Coulee Dam's FY 2012 Sidewalk Maintenance Project
2-E-878(003)-1
2-E-878(003)-1
FY 2012 Sidewalk Maintenance Project
Multiple Locations
FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $98,618
County: Okanogan/Douglas/Grant | Legislative District: 12 | Project Length: 0.34 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/16/2011
Project Information
Lead Agency | COULEE DAM |
Funding Year | 2012 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.34 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Carol Visker |
Contact Email | cdclerk@couleedam.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/16/2011 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2010 | |
Delayed Project Date | 07/01/2013 | |
Predesign Approval | ||
Design Approval | 12/15/2010 | 01/19/2011 |
Bid Auth. Approval | 06/01/2011 | 01/19/2011 |
Construction Approval | 05/31/2011 | 08/11/2011 |
Project Closeout | 12/31/2011 | 11/03/2011 |
Audit Date | 11/16/2011 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 7,000 |
Right of Way | 0 | 0 |
Total Design | 0 | 7,000 |
Construction Engineering | 0 | 11,692 |
Construction Contract | 99,746 | 79,926 |
Other Construction | 0 | 0 |
Total Construction | 99,746 | 91,618 |
Funding Increase | 3,778 | |
Funding Surplus | - 4,906 | |
Total TIB Funding | 98,618 | 98,618 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COULEE DAM | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will repair damaged segments of sidewalk along the north side of Camas Street between 11th Street and Crest Drive and along the north side of Central Drive between 12th Street and Crest Drive.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |