TIB Project Information

Town of Conconully's 2024 Street Maintenance

2-E-877(005)-1

2-E-877(005)-1
2024 Street Maintenance

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $92,667

County: Okanogan   |   Legislative District: 7   |   Project Length: 0.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 10/01/2024

Project Information

Lead Agency CONCONULLY
Funding Year 2025
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 4
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Zach Claussen
Contact Email zclaussen@townofconconully.com
TIB Engineer Andrew Beagle
Last Payment Date 10/01/2024

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
Predesign Approval
Design Approval 02/15/2024 01/24/2024
Bid Auth. Approval 05/15/2024 01/24/2024
Construction Approval 06/24/2024 07/24/2024
Project Closeout 10/31/2024 09/24/2024
Audit Date   10/01/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 114,500 97,667
Other Construction 0 0
Total Construction 114,500 97,667
     
Funding Surplus - 21,833  
Total TIB Funding 92,667 97,667

Local Funding Partners

Funding Amount Percent
CONCONULLY 5,000 5.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 5,000 5.1%

Project Description

Town-wide crack sealing and pavement repair at the Main Street and Broadway Street intersection.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments