Town of Conconully's FY 2014 Overlay Project

2-E-877(002)-1

2-E-877(002)-1
FY 2014 Overlay Project

Multiple Locations

FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $131,875

County: Okanogan   |   Legislative District: 7   |   Project Length: 0.25   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 02/19/2014

Project Information

Lead Agency CONCONULLY
Funding Year 2014
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 4
Federal Route Number 9999
Project Length 0.25 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Zachary Claussen
Contact Email zclaussen@townofconconully.com
TIB Engineer Andrew Beagle
Last Payment Date 02/19/2014

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2012
Delayed Project Date 07/01/2015  
Predesign Approval
Design Approval 01/01/2013 02/27/2013
Bid Auth. Approval 06/01/2013 07/18/2013
Construction Approval 08/01/2013 08/13/2013
Project Closeout 02/01/2014 01/31/2014
Audit Date   02/19/2014
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 5,000 12,400
Right of Way 0 0
Total Design 5,000 12,400
     
Construction Engineering 6,200 5,434
Construction Contract 58,800 114,040
Other Construction 0 0
Total Construction 65,000 119,475
     
Funding Increase 61,875  
Total TIB Funding 131,875 131,875

Local Funding Partners

Funding Amount Percent
CONCONULLY 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Provide pavement repair and crack sealing and overlay the roadway surfaces on Broadway - W Park Entrance to A Street Silver - Lottie to Main Street

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments