City of Brewster's FY 2019 Seal Coat Project

2-E-876(003)-1

2-E-876(003)-1
FY 2019 Seal Coat Project

Multiple Locations

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $69,435

County: Okanogan   |   Legislative District: 12   |   Project Length: 0.18   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 12/12/2018

Project Information

Lead Agency BREWSTER
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.18 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Lee Webster
Contact Email Lee.Webster@brewsterwa.us
TIB Engineer Andrew Beagle
Last Payment Date 12/12/2018

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 04/17/2018
Bid Auth. Approval 05/01/2018 04/17/2018
Construction Approval 06/01/2018 04/17/2018
Project Closeout 12/31/2018 11/27/2018
Audit Date   12/12/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 39,779 42,944
Other Construction 0 30,147
Total Construction 39,779 73,091
     
Funding Increase 29,656  
Total TIB Funding 69,435 73,091

Local Funding Partners

Funding Amount Percent
BREWSTER 3,655 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 3,655 5.0%

Project Description

The project seals cracks, repairs pavement and chip seals the surface.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.