Town of Wilbur's FY 2022 Seal Coat Project

2-E-875(006)-1

2-E-875(006)-1
FY 2022 Seal Coat Project

Multiple Locations

FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $8,734

County: Lincoln   |   Legislative District: 13   |   Project Length: 0.13   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/01/2021

Project Information

Lead Agency WILBUR
Funding Year 2022
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 5
Federal Route Number 9999
Project Length 0.13 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Dave Bjornson
Contact Email tow@wilburwa.com
TIB Engineer Andrew Beagle
Last Payment Date 11/01/2021

Project Schedule

  Target Date Actual Date
Project Selection Date   02/23/2021
Delayed Project Date 07/01/2023  
Predesign Approval 02/01/2021
Design Approval 03/01/2021 04/01/2021
Bid Auth. Approval 04/01/2021 04/01/2021
Construction Approval 05/01/2021 04/02/2021
Project Closeout 10/31/2021 10/21/2021
Audit Date   11/01/2021
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 5,000 8,734
Other Construction 0 0
Total Construction 5,000 8,734
     
Funding Increase 3,734  
Total TIB Funding 8,734 8,734

Local Funding Partners

Funding Amount Percent
WILBUR 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

County to chip seal section of Brace Street from Cliff Ave to SR 2.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.