Regent Avenue is a primary east-west route in Wilbur. The pavement is showing signs of distress. The overall pavement condition rating for the street from Prince Street to Bell Street is 64.
Projects — TIB Project Information
TIB Project Information
Town of Wilbur's FY 2017 Seal Coat Project
2-E-875(004)-1
2-E-875(004)-1
FY 2017 Seal Coat Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $97,380
County: Lincoln | Legislative District: 13 | Project Length: 0.87 | TIB Engineer: Andrew Beagle | Last Payment Date: 06/21/2018
Project Information
Lead Agency | WILBUR |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.87 mi. |
ADT | 200 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Gloria Kuchenbuch |
Contact Email | tow@wilburwa.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 06/21/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 05/02/2016 |
Bid Auth. Approval | 04/01/2016 | 05/02/2016 |
Construction Approval | 06/01/2016 | 05/02/2016 |
Project Closeout | 07/01/2018 | 01/17/2019 |
Audit Date | 01/30/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 10,000 | 0 |
Right of Way | 0 | 0 |
Total Design | 10,000 | 0 |
Construction Engineering | 0 | 2,381 |
Construction Contract | 181,627 | 94,999 |
Other Construction | 0 | 0 |
Total Construction | 181,627 | 97,379 |
Funding Surplus | - 94,247 | |
Total TIB Funding | 97,380 | 97,379 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WILBUR | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project repairs pavement, seals cracks and chip seals Prince Street and Regent Avenue from SR 21 to Bell Street.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |