TIB Project Information

Town of Wilbur's FY 2010 Seal Coat Project

2-E-875(001)-1

2-E-875(001)-1
FY 2010 Seal Coat Project

Multiple Locations

FY 2010 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $31,395

County: Lincoln   |   Legislative District: 13   |   Project Length: 0.58   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/04/2009

Project Information

Lead Agency WILBUR
Funding Year 2010
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 5
Federal Route Number 9999
Project Length 0.58 mi.
ADT 200
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Jim Pope
Contact Email Jimp@odessaoffice.com
TIB Engineer Andrew Beagle
Last Payment Date 11/04/2009

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2008
Delayed Project Date 07/01/2011  
Predesign Approval
Design Approval 01/01/2009 02/10/2009
Bid Auth. Approval 01/01/2009 02/10/2009
Construction Approval 03/01/2009 04/10/2009
Project Closeout 10/31/2009 01/20/2010
Audit Date   01/20/2010
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 12,155 0
Construction Contract 36,935 31,395
Other Construction 0 0
Total Construction 49,090 31,395
     
Funding Surplus - 17,695  
Total TIB Funding 31,395 31,395

Local Funding Partners

Funding Amount Percent
WILBUR 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Chip Seal the following segments S Division Street - Trinity St to Regent St S Division Street - Front St to Main St (SR 2) Front Street - SR 21 to Brace St

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.