Projects — TIB Project Information
TIB Project Information
Town of Reardan's 2021 Overlay
2-E-873(006)-1
2-E-873(006)-1
2021 Overlay
Multiple Locations
FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $364,819
County: Lincoln | Legislative District: 13 | Project Length: 0.12 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/02/2023
Project Information
Lead Agency | REARDAN |
Funding Year | 2023 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.12 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Megan Kamstra |
Contact Email | clerk@townofreardan.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/02/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
Predesign Approval | ||
Design Approval | 02/01/2022 | 12/07/2021 |
Bid Auth. Approval | 03/15/2023 | 04/11/2023 |
Construction Approval | 04/28/2023 | 05/12/2023 |
Project Closeout | 09/30/2023 | 09/11/2023 |
Audit Date | 10/02/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 21,509 | 21,712 |
Right of Way | 0 | 0 |
Total Design | 21,509 | 21,712 |
Construction Engineering | 26,886 | 24,263 |
Construction Contract | 247,351 | 318,844 |
Other Construction | 0 | 0 |
Total Construction | 274,237 | 343,107 |
Funding Increase | 69,073 | |
Total TIB Funding | 364,819 | 364,819 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
REARDAN | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Project will patch potholes, crack seal, apply HMA pre-level and 1.5 HMA overlay, and shoulder rock. Water line is locate in west gravel shoulder and is not under road. 2 ADA ramps on Birch St are not compliant and will be replaced.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |