Town of Reardan's FY 2019 Rehabilitation Project

2-E-873(004)-1

2-E-873(004)-1
FY 2019 Rehabilitation Project

FDR w/Overlay - Cottonwood; FDR w/Chip - Spokane/Green

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $307,237

County: Lincoln   |   Legislative District: 13   |   Project Length: 0.35   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 03/01/2019

Project Information

Lead Agency REARDAN
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 5
Federal Route Number 9999
Project Length 0.35 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Jeff Evers
Contact Email townofreardan@gmail.com
TIB Engineer Andrew Beagle
Last Payment Date 03/01/2019

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 01/24/2018
Bid Auth. Approval 04/01/2018 05/01/2018
Construction Approval 05/15/2018 05/29/2018
Project Closeout 12/31/2018 02/26/2019
Audit Date   03/01/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 24,080 24,198
Right of Way 0 0
Total Design 24,080 24,198
     
Construction Engineering 30,637 31,792
Construction Contract 218,241 254,277
Other Construction 0 0
Total Construction 248,878 286,069
     
Funding Increase 34,279  
Total TIB Funding 307,237 310,268

Local Funding Partners

Funding Amount Percent
REARDAN 3,031 1.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 3,031 1.0%

Project Description

The project improvements include full depth reclamation (FDR) of the selected street sections to provide adequate base. On Cottonwood, the project provides a HMA overlay to cap the FDR. Chip seal caps the FDR on Spokane Avenue and Green Street.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.