The existing sidewalks are cracked and buckled. They serve as primary walk routes between the school complex and central business district.
Projects — TIB Project Information
TIB Project Information
Town of Reardan's FY 2013 Sidewalk Maintenance Project
2-E-873(003)-1
2-E-873(003)-1
FY 2013 Sidewalk Maintenance Project
Multiple Locations
FY 2013 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $85,675
County: Lincoln | Legislative District: 13 | Project Length: 0.16 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/13/2012
Project Information
Lead Agency | REARDAN |
Funding Year | 2013 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.16 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Bruce Johnson |
Contact Email | townofreardan@gmail.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/13/2012 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2011 | |
Delayed Project Date | 07/01/2014 | |
Predesign Approval | ||
Design Approval | 01/01/2012 | 01/23/2012 |
Bid Auth. Approval | 05/01/2012 | 01/23/2012 |
Construction Approval | 06/01/2012 | 07/06/2012 |
Project Closeout | 10/31/2012 | 10/31/2012 |
Audit Date | 11/13/2012 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 14,045 | 9,250 |
Right of Way | 0 | 0 |
Total Design | 14,045 | 9,250 |
Construction Engineering | 9,363 | 10,472 |
Construction Contract | 70,224 | 65,953 |
Other Construction | 0 | 0 |
Total Construction | 79,587 | 76,425 |
Funding Surplus | - 7,957 | |
Total TIB Funding | 85,675 | 85,675 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
REARDAN | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project replaces deficient sidewalk and curb along Birch and Laurel streets between Broadway (SR 2) and Spokane Street. ADA ramp upgrades ensure access to the sidewalk.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |