The existing sidewalk on the south side of Broadway (SR 2) between Aspen and Cedar is in disrepair. The surface is cracked and buckled.
Projects — TIB Project Information
TIB Project Information
Town of Reardan's FY 2009 Sidewalk Maintenance Project
2-E-873(001)-1
2-E-873(001)-1
FY 2009 Sidewalk Maintenance Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $27,660
County: Lincoln | Legislative District: 13 | Project Length: 0.12 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/12/2008
Project Information
Lead Agency | REARDAN |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 5 |
Federal Route Number | 0002 |
Project Length | 0.12 mi. |
ADT | 500 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Bruce Johnson |
Contact Email | townofreardan@gmail.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/12/2008 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/01/2008 | 02/06/2008 |
Bid Auth. Approval | 01/01/2008 | 02/06/2008 |
Construction Approval | 09/08/2008 | 09/10/2008 |
Project Closeout | 12/31/2008 | 11/12/2008 |
Audit Date | 11/12/2008 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 16,300 | 27,660 |
Other Construction | 0 | 0 |
Total Construction | 16,300 | 27,660 |
Funding Increase | 11,360 | |
Total TIB Funding | 27,660 | 27,660 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
REARDAN | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Repair sidewalk and add ADA ramps along Broadway Avenue (SR-2) between Aspen Street and Cedar Street.
Existing Condition
Project Benefits
- Adds ADA access ;
- Removes hazards
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |