Pavement cracks and pavement degradation exists on many roadway areas in Town.
Projects — TIB Project Information
TIB Project Information
Town of Odessa's 2024 Maintenance Project
2-E-872(004)-1
2-E-872(004)-1
2024 Maintenance Project
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $165,377
County: Lincoln | Legislative District: 9 | Project Length: 0.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 09/13/2024
Project Information
Lead Agency | ODESSA |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Trent Ward |
Contact Email | tward@centurywest.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 09/13/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
Predesign Approval | ||
Design Approval | 02/01/2024 | 12/13/2023 |
Bid Auth. Approval | 04/30/2024 | 12/13/2023 |
Construction Approval | 06/15/2024 | 05/17/2024 |
Project Closeout | 12/31/2024 | 09/09/2024 |
Audit Date | 09/13/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 190,630 | 165,377 |
Other Construction | 0 | 0 |
Total Construction | 190,630 | 165,377 |
Funding Increase | 47,895 | |
Funding Surplus | - 73,148 | |
Total TIB Funding | 165,377 | 165,377 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ODESSA | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Clean and install crack sealant and dig out and repair areas of pavement degradation that are not practical to crack seal or chip seal
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |