Town of Odessa's FY 2019 Rehabilitation Project
2-E-872(003)-3
2-E-872(003)-3
FY 2019 Rehabilitation Project
2019 Construction Phase
FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $42,438
County: Lincoln | Legislative District: 13 | Project Length: 1.42 | TIB Engineer: Andrew Beagle | Last Payment Date: 03/24/2020
Project Information
Lead Agency | ODESSA |
Funding Year | 2019 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 1.42 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Denise Snead |
Contact Email | clerk@odessaoffice.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 03/24/2020 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/17/2017 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | ||
Bid Auth. Approval | 05/02/2019 | 05/02/2019 |
Construction Approval | 06/01/2019 | 06/19/2019 |
Project Closeout | 03/01/2020 | 03/10/2020 |
Audit Date | 03/24/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 5,824 | 47,735 |
Construction Contract | 43,029 | 291,767 |
Other Construction | 0 | 0 |
Total Construction | 48,853 | 339,502 |
Funding Surplus | - 6,415 | |
Total TIB Funding | 42,438 | 339,502 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ODESSA | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
FEMA | 254,626 | 75.0% |
WA EMD | 42,438 | 12.5% |
Total Local Funding | 297,064 | 87.5% |
Project Description
In conjunction with FEMA and State Emergency Management funding, the project rehabilitates streets damaged by winter weather.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |