Town of Odessa's FY 2019 Rehabilitation Project

2-E-872(003)-1

2-E-872(003)-1
FY 2019 Rehabilitation Project

Multiple Locations

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $39,511

County: Lincoln   |   Legislative District: 13   |   Project Length: 1.42   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 09/20/2022

Project Information

Lead Agency ODESSA
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 5
Federal Route Number 9999
Project Length 1.42 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Denise Snead
Contact Email clerk@odessaoffice.com
TIB Engineer Andrew Beagle
Last Payment Date 09/20/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 12/27/2017
Bid Auth. Approval 01/31/2021 01/19/2021
Construction Approval 02/28/2021 02/18/2021
Project Closeout 08/31/2022 09/06/2022
Audit Date   09/27/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 19,415 0
Right of Way 0 0
Total Design 19,415 0
     
Construction Engineering 13,591 39,296
Construction Contract 100,293 276,792
Other Construction 0 0
Total Construction 113,884 316,088
     
Funding Surplus - 93,788  
Total TIB Funding 39,511 316,088

Local Funding Partners

Funding Amount Percent
ODESSA 0 0.0%
WSDOT Funding 0 0.0%
FEMA  276,577 87.5%
 
 
 
 
 
 
 
Total Local Funding 276,577 87.5%

Project Description

In conjunction with FEMA and State Emergency Management funding, the project rehabilitates streets damaged by winter weather.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.