Projects — TIB Project Information
TIB Project Information
City of Harrington's FY 2020 Seal Coat Project
2-E-871(002)-1
2-E-871(002)-1
FY 2020 Seal Coat Project
Multiple Locations
FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $54,128
County: Lincoln | Legislative District: 13 | Project Length: 0.18 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/14/2022
Project Information
Lead Agency | HARRINGTON |
Funding Year | 2020 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.18 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Janice Cepeda |
Contact Email | harringtoncity@gmail.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 01/14/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 01/15/2019 |
Bid Auth. Approval | 04/01/2019 | 01/15/2019 |
Construction Approval | 05/01/2019 | 06/28/2021 |
Project Closeout | 12/31/2021 | 01/06/2022 |
Audit Date | 01/14/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 77,990 | 54,128 |
Other Construction | 0 | 0 |
Total Construction | 77,990 | 54,128 |
Funding Surplus | - 23,862 | |
Total TIB Funding | 54,128 | 54,128 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
HARRINGTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project provides pavement repair, crack seal and chip seal of the approved segments. The city plans to contract the prep work in 2019. Lincoln County agreed to chip seal the streets in 2020.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |