The existing surface is showing signs of deterioration and ready for maintenance to extend life on Maxwell between 12th (SR 28) and 7th.
Projects — TIB Project Information
TIB Project Information
City of Davenport's FY 2019 Seal Coat Project
2-E-870(003)-1
2-E-870(003)-1
FY 2019 Seal Coat Project
Multiple Locations
FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $17,744
County: Lincoln | Legislative District: 13 | Project Length: 0.32 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/12/2018
Project Information
Lead Agency | DAVENPORT |
Funding Year | 2019 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.32 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Steve Goemmel |
Contact Email | sjgoemmel@centurytel.net |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/12/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/17/2017 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2018 | 12/28/2017 |
Bid Auth. Approval | 06/01/2018 | 12/28/2017 |
Construction Approval | 07/01/2018 | 12/28/2017 |
Project Closeout | 12/31/2018 | 10/01/2018 |
Audit Date | 10/12/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 86 |
Construction Contract | 18,482 | 9,252 |
Other Construction | 0 | 8,406 |
Total Construction | 18,482 | 17,744 |
Funding Surplus | - 738 | |
Total TIB Funding | 17,744 | 17,744 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
DAVENPORT | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project seals cracks, repairs pavement and chip seals the surface on Maxwell between 12th (SR 28) and 7th.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |