The pavement condition ratings of the segment are as follows Navar Street - 1st St to 6th St 63
Projects — TIB Project Information
TIB Project Information
Town of Wilson Creek's FY 2019 Seal Coat Project
2-E-867(006)-1
2-E-867(006)-1
FY 2019 Seal Coat Project
Multiple Locations
FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $171,199
County: Grant | Legislative District: 13 | Project Length: 0.43 | TIB Engineer: Andrew Beagle | Last Payment Date: 05/06/2021
Project Information
Lead Agency | WILSON CREEK |
Funding Year | 2019 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.43 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Kaci Anderson |
Contact Email | clerk@wilsoncreekwa.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 05/06/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/17/2017 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2018 | 02/13/2018 |
Bid Auth. Approval | 04/01/2018 | 02/13/2018 |
Construction Approval | 05/01/2018 | 02/13/2018 |
Project Closeout | 02/28/2021 | 03/01/2021 |
Audit Date | 05/06/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 8,300 | 16,589 |
Right of Way | 0 | 0 |
Total Design | 8,300 | 16,589 |
Construction Engineering | 8,300 | 0 |
Construction Contract | 185,295 | 154,610 |
Other Construction | 0 | 0 |
Total Construction | 193,595 | 154,610 |
Funding Surplus | - 30,696 | |
Total TIB Funding | 171,199 | 171,199 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WILSON CREEK | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will complete pavement repair on the half lane near the embankment and then chip seal the rest. The project will also include pavement striping, quarry spall for stormwater dispersion/embankment stabilization
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |