City of Warden's FY 2019 Rehabilitation Project

2-E-866(004)-1

2-E-866(004)-1
FY 2019 Rehabilitation Project

Multiple Locations

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $238,286

County: Grant   |   Legislative District: 13   |   Project Length: 0.30   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/02/2020

Project Information

Lead Agency WARDEN
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 4
Federal Route Number 9999
Project Length 0.30 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Kristine Shuler
Contact Email kshuler@cityofwarden.org
TIB Engineer Jonathan Heusman
Last Payment Date 03/02/2020

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 01/16/2018
Bid Auth. Approval 04/01/2019 04/04/2019
Construction Approval 04/30/2019 05/20/2019
Project Closeout 01/31/2020 02/13/2020
Audit Date   03/02/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 25,213 26,540
Right of Way 0 0
Total Design 25,213 26,540
     
Construction Engineering 25,203 26,530
Construction Contract 168,083 197,758
Other Construction 0 0
Total Construction 193,286 224,288
     
Funding Increase 25,084  
Funding Surplus - 5,297  
Total TIB Funding 238,286 250,828

Local Funding Partners

Funding Amount Percent
WARDEN 12,542 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 12,542 5.0%

Project Description

Segment one will be pulverized for 1,600 feet with a width of 30 feet. The new pavement section will be 24 feet wide with two 12 foot lanes. A geotech report will be developed to determine the quality of the existing subgrade. It is likely that the center 24 feet of the roadway will be treated with CTB prior to paving. 2' of crushed gravel surfacing will be added to the new 3' wide shoulders.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.