TIB Project Information

City of Soap Lake's FY 2019 Rehabilitation Project

2-E-865(009)-1

2-E-865(009)-1
FY 2019 Rehabilitation Project

Multiple Locations

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $333,034

County: Grant   |   Legislative District: 12   |   Project Length: 0.32   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 02/03/2020

Project Information

Lead Agency SOAP LAKE
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.32 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Raymond Gravelle
Contact Email sladmin@smwireless.net
TIB Engineer Andrew Beagle
Last Payment Date 02/03/2020

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 02/05/2018
Bid Auth. Approval 03/01/2018 05/15/2018
Construction Approval 01/16/2019 02/15/2019
Project Closeout 12/31/2019 01/07/2019
Audit Date   02/03/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 33,700 33,700
Right of Way 0 0
Total Design 33,700 33,700
     
Construction Engineering 33,700 33,700
Construction Contract 225,100 265,634
Other Construction 0 0
Total Construction 258,800 299,334
     
Funding Increase 40,534  
Total TIB Funding 333,034 333,034

Local Funding Partners

Funding Amount Percent
SOAP LAKE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project pulverizes the existing street surfaces adding cement treated base if necessary and overlays with hot mix asphalt. The approved streets provide direct access to Soap Lake Park. It is currently undergoing a $393,000 renovation project.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments