The PCR score for these sections of roadway inidicates a seal coat is the best option to extend the life of the roadway.
Projects — TIB Project Information
TIB Project Information
City of Soap Lake's FY 2009 Seal Coat Project
2-E-865(002)-1
2-E-865(002)-1
FY 2009 Seal Coat Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $57,005
County: Grant | Legislative District: 12 | Project Length: 0.77 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/20/2011
Project Information
Lead Agency | SOAP LAKE |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12, 13 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.77 mi. |
ADT | 250 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | Debbie Amundson |
Contact Email | cityhall@soaplakecity.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 01/20/2011 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/01/2008 | 02/28/2008 |
Bid Auth. Approval | 01/01/2008 | 02/28/2008 |
Construction Approval | 07/01/2008 | 07/31/2008 |
Project Closeout | 11/01/2010 | 01/18/2011 |
Audit Date | 01/20/2011 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 55,433 | 46,200 |
Other Construction | 0 | 10,805 |
Total Construction | 55,433 | 57,005 |
Funding Increase | 1,572 | |
Total TIB Funding | 57,005 | 57,005 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SOAP LAKE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
2008 Work - Seal Coat the following segments 2nd Avenue - Canna Street to Daisy Street 2nd Place SE - 6th Street to 7th Street Buttercup Street - 6th Street to 7th Street E Main Street - Daisy Street to Iris Street 2010 Work - City Crack Seal Lakeshore Dr - Juniper St to Fir St Fir St - Lakeshore Dr to 2nd Ave 2010 Work - City Crack Seal, Spot Repair, County Chip Seal Hemlock St - Lakeshore Dr to 2nd Ave 6th St - Division St to Daisy St
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |