Town of Mattawa's FY 2019 Rehabilitation Project
2-E-862(010)-1
2-E-862(010)-1
FY 2019 Rehabilitation Project
Multiple Locations
FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $370,911
County: Grant | Legislative District: 13 | Project Length: 0.46 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/03/2018
Project Information
Lead Agency | MATTAWA |
Funding Year | 2019 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.46 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Juan Ledezma |
Contact Email | jledezma@cityofmattawa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/03/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/17/2017 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2018 | 01/23/2018 |
Bid Auth. Approval | 05/01/2018 | 05/31/2018 |
Construction Approval | 06/28/2018 | 07/06/2018 |
Project Closeout | 10/31/2018 | 11/13/2018 |
Audit Date | 12/03/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 44,700 | 44,606 |
Right of Way | 0 | 0 |
Total Design | 44,700 | 44,606 |
Construction Engineering | 44,700 | 37,329 |
Construction Contract | 299,100 | 288,976 |
Other Construction | 0 | 0 |
Total Construction | 343,800 | 326,305 |
Funding Increase | 18,919 | |
Funding Surplus | - 36,508 | |
Total TIB Funding | 370,911 | 370,911 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MATTAWA | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The work provides for pulverizing and overlaying Portage Avenue S, from 4th Street to 8th Street, including but not limited to pulverizing the existing pavement, excavation, grading, subgrade preparation, crushed surfacing material, hot mix asphalt pavement, pavement marking, miscellaneous surface restoration, traffic control, and all other appurtenances required to complete the work.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |