The PCR ratings for the selected segments are as follows Boundary - Government Rd to Saddle Mountain Rd 16 Portage Avenue - Government Rd to Saddle Mountain Rd 49
Projects — TIB Project Information
TIB Project Information
Town of Mattawa's FY 2014 Red Town Project
2-E-862(005)-1
2-E-862(005)-1
FY 2014 Red Town Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $382,705
County: Grant | Legislative District: 13 | Project Length: 0.45 | TIB Engineer: Jonathan Heusman | Last Payment Date: 01/14/2014
Project Information
Lead Agency | MATTAWA |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.45 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Gary Crowder |
Contact Email | robin@cityofmattawa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 01/14/2014 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 01/01/2013 | 12/13/2012 |
Bid Auth. Approval | 05/01/2013 | 07/09/2013 |
Construction Approval | 08/01/2013 | 08/19/2013 |
Project Closeout | 12/31/2013 | 01/28/2014 |
Audit Date | 01/31/2014 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 40,400 | 42,500 |
Right of Way | 0 | 0 |
Total Design | 40,400 | 42,500 |
Construction Engineering | 40,400 | 38,083 |
Construction Contract | 319,200 | 322,264 |
Other Construction | 0 | 0 |
Total Construction | 359,600 | 360,347 |
Funding Increase | 8,157 | |
Funding Surplus | - 25,452 | |
Total TIB Funding | 382,705 | 402,847 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MATTAWA | 20,142 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 20,142 | 5.0% |
Project Description
The project recycles the existing surface to strengthen the base. A three-in hot mix asphalt overlay provides a smooth, low maintenance surface.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |