This town has been designated a red town because of the overall poor condition of the streets. The average PCR score for Cooper Street is 16.
Projects — TIB Project Information
TIB Project Information
Town of Mattawa's FY 2010 Overlay - Cooper St
2-E-862(003)-1
2-E-862(003)-1
FY 2010 Overlay - Cooper St
Portage St to Boundary St
FY 2010 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $189,227
County: Grant | Legislative District: 13 | Project Length: 0.53 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/27/2010
Project Information
Lead Agency | MATTAWA |
Funding Year | 2010 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.53 mi. |
ADT | 2,000 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Diane Martinez |
Contact Email | townhall@gemsi.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 10/27/2010 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 01/29/2010 | |
Delayed Project Date | 07/01/2012 | |
Predesign Approval | ||
Design Approval | 01/25/2010 | 01/25/2010 |
Bid Auth. Approval | 04/01/2010 | 03/05/2010 |
Construction Approval | 05/01/2010 | 04/14/2010 |
Project Closeout | 10/01/2010 | 10/25/2010 |
Audit Date | 10/27/2010 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 30,735 | 30,735 |
Right of Way | 0 | 0 |
Total Design | 30,735 | 30,735 |
Construction Engineering | 26,818 | 16,053 |
Construction Contract | 178,784 | 142,440 |
Other Construction | 0 | 0 |
Total Construction | 205,602 | 158,492 |
Funding Surplus | - 47,110 | |
Total TIB Funding | 189,227 | 189,227 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MATTAWA | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Red town project. The project consist of base preparation and 2 in overlay on Cooper Street from Portage St to Boundary St.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |