TIB Project Information

Town of Mattawa's FY 2009 Overlay Project

2-E-862(001)-1

2-E-862(001)-1
FY 2009 Overlay Project

Multiple Locations

FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $211,700

County: Grant   |   Legislative District: 13   |   Project Length: 0.56   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 12/01/2008

Project Information

Lead Agency MATTAWA
Funding Year 2009
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 4
Federal Route Number 9999
Project Length 0.56 mi.
ADT 200
Functional Class Local Access
Type of Work Resurfacing
Project Contact Patricia Gerdes
Contact Email townhall@gemsi.com
TIB Engineer Jonathan Heusman
Last Payment Date 12/01/2008

Project Schedule

  Target Date Actual Date
Project Selection Date   07/10/2008
Delayed Project Date 07/01/2011  
Predesign Approval
Design Approval
Bid Auth. Approval 06/15/2008 06/15/2008
Construction Approval 07/15/2008 07/11/2008
Project Closeout 09/15/2008 11/21/2008
Audit Date   12/01/2008
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 225,336 211,700
Other Construction 0 0
Total Construction 225,336 211,700
     
Funding Surplus - 13,636  
Total TIB Funding 211,700 211,700

Local Funding Partners

Funding Amount Percent
MATTAWA 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project consist of base preparation and 2 in overlay of the following segments Portage Avenue - Government Wy to 4th St 4th Street - Portage Ave to Selkirk Ave

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments