Town of Hartline's FY 2012 Seal Coat Project
2-E-860(003)-1
2-E-860(003)-1
FY 2012 Seal Coat Project
Multiple Locations
FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $17,807
County: Grant | Legislative District: 12 | Project Length: 0.72 | TIB Engineer: Andrew Beagle | Last Payment Date: 03/15/2013
Project Information
Lead Agency | HARTLINE |
Funding Year | 2012 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.72 mi. |
ADT | 150 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | Helen Marie Groh |
Contact Email | townofhartline@yahoo.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 03/15/2013 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2010 | |
Delayed Project Date | 07/01/2013 | |
Predesign Approval | ||
Design Approval | 12/15/2010 | 02/23/2011 |
Bid Auth. Approval | 06/01/2011 | 02/23/2011 |
Construction Approval | 08/01/2012 | 07/01/2012 |
Project Closeout | 02/01/2013 | 02/28/2013 |
Audit Date | 03/15/2013 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 18,586 | 17,807 |
Other Construction | 0 | 0 |
Total Construction | 18,586 | 17,807 |
Funding Surplus | - 779 | |
Total TIB Funding | 17,807 | 17,807 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
HARTLINE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will chip seal the following four segments Caldwell Street between Clark St and Hill St Clark Street between May St and Main St Leonard Street between May St and Caldwell St May Street between Division St and Leonard St
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |