City of Grand Coulee's FY 2020 Overlay Project
2-E-859(004)-1
2-E-859(004)-1
FY 2020 Overlay Project
FEMA Repair Sites
FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $82,017
County: Grant | Legislative District: 12 | Project Length: 0.19 | TIB Engineer: Andrew Beagle | Last Payment Date: 12/01/2020
Project Information
Lead Agency | GRAND COULEE |
Funding Year | 2020 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.19 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Dennis Francis |
Contact Email | shopboss@couleemail.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 12/01/2020 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 01/14/2019 |
Bid Auth. Approval | 05/01/2019 | 07/16/2019 |
Construction Approval | 08/01/2019 | 10/02/2019 |
Project Closeout | 07/01/2020 | 11/16/2020 |
Audit Date | 12/01/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 5,100 | 33,353 |
Right of Way | 0 | 0 |
Total Design | 5,100 | 33,353 |
Construction Engineering | 5,100 | 46,595 |
Construction Contract | 96,549 | 576,186 |
Other Construction | 0 | 0 |
Total Construction | 101,649 | 622,781 |
Funding Surplus | - 24,732 | |
Total TIB Funding | 82,017 | 656,134 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRAND COULEE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
FEMA | 492,101 | 75.0% |
Washington State Emergency Management | 82,017 | 12.5% |
Total Local Funding | 574,118 | 87.5% |
Project Description
In coordination with FEMA, project provides pavement repair for roadway surfaces throughout the city.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |