The existing surfaces are showing signs of deterioration with localized alligator and transverse cracking. The current pavement condition ratings are 58 - 2nd St - Main to B 58 - Main St - SR 155 to 2nd 58 - Spokane Way - SR 155 to Federal 63 - Spokane Way - Federal to SR 174
Projects — TIB Project Information
TIB Project Information
City of Grand Coulee's FY 2019 Seal Coat Project
2-E-859(003)-1
2-E-859(003)-1
FY 2019 Seal Coat Project
Multiple Locations
FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $185,555
County: Grant | Legislative District: 12 | Project Length: 0.76 | TIB Engineer: Andrew Beagle | Last Payment Date: 05/01/2019
Project Information
Lead Agency | GRAND COULEE |
Funding Year | 2019 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.76 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Dennis Francis |
Contact Email | shopboss@couleemail.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 05/01/2019 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/17/2017 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2018 | 02/14/2018 |
Bid Auth. Approval | 04/01/2018 | 02/14/2018 |
Construction Approval | 05/01/2018 | 06/29/2018 |
Project Closeout | 01/31/2019 | 04/15/2019 |
Audit Date | 05/01/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 7,700 | 7,237 |
Right of Way | 0 | 0 |
Total Design | 7,700 | 7,237 |
Construction Engineering | 7,700 | 8,164 |
Construction Contract | 171,674 | 170,155 |
Other Construction | 0 | 0 |
Total Construction | 179,374 | 178,319 |
Funding Increase | 2,392 | |
Funding Surplus | - 3,911 | |
Total TIB Funding | 185,555 | 185,555 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRAND COULEE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project includes preparation of the segments and application of a chip seal to preserve the surface on the following segments 2nd St - Main to B Main St - SR 155 to 2nd Spokane Way - SR 155 to Federal Spokane Way - Federal to SR 174
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |