TIB Project Information

City of Grand Coulee's 2017 Emergency Pavement Repair Project

2-E-859(002)-1

2-E-859(002)-1
2017 Emergency Pavement Repair Project

Various Locations

FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $50,000

County: Grant   |   Legislative District: 12   |   Project Length: 0.10   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 08/10/2017

Project Information

Lead Agency GRAND COULEE
Funding Year 2018
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dennis Francis
Contact Email shopboss@gccitywa.org
TIB Engineer Andrew Beagle
Last Payment Date 08/10/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   06/01/2017
Delayed Project Date 07/01/2019  
Predesign Approval
Design Approval 06/15/2017 06/22/2017
Bid Auth. Approval 06/15/2017 06/22/2017
Construction Approval 06/15/2017 06/22/2017
Project Closeout 08/31/2017 08/03/2017
Audit Date   08/10/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 50,000 51,779
Other Construction 0 0
Total Construction 50,000 51,779
     
Total TIB Funding 50,000 51,779

Local Funding Partners

Funding Amount Percent
GRAND COULEE 1,779 3.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,779 61.8%

Project Description

See approved scope

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments