Projects — TIB Project Information
TIB Project Information
City of George's FY 2018 Rehabilitation Project
2-E-858(003)-1
2-E-858(003)-1
FY 2018 Rehabilitation Project
Multiple Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $264,354
County: Grant | Legislative District: 13 | Project Length: 0.24 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/14/2017
Project Information
Lead Agency | GEORGE |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.24 mi. |
ADT | 350 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Tina Evenson |
Contact Email | geoclerk@smwireless.net |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/14/2017 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 12/06/2016 |
Bid Auth. Approval | 04/01/2017 | 06/19/2017 |
Construction Approval | 07/10/2017 | 09/11/2017 |
Project Closeout | 11/30/2017 | 12/04/2017 |
Audit Date | 12/14/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 24,106 | 25,375 |
Right of Way | 0 | 0 |
Total Design | 24,106 | 25,375 |
Construction Engineering | 24,106 | 26,241 |
Construction Contract | 184,538 | 233,276 |
Other Construction | 0 | 0 |
Total Construction | 208,644 | 259,517 |
Funding Increase | 50,000 | |
Funding Surplus | - 18,396 | |
Total TIB Funding | 264,354 | 284,892 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GEORGE | 20,538 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 20,538 | 5.0% |
Project Description
This project pulverizes and overlays Frontage Road between Royal Anne Drive and Washington Street. Providing two 12-foot lanes to accommodate the truck traffic using this segment to access the County road extending to the Northeast, as well as the truck scales.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |