 Projects — TIB Project Information

TIB Project Information

Town of Electric City's FY 2013 Seal Coat Project

2-E-857(003)-1

2-E-857(003)-1
FY 2013 Seal Coat Project

Multiple Locations

FY 2013 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $61,110

County: Grant   |   Legislative District: 12   |   Project Length: 1.86   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 01/07/2013

Project Information

Lead Agency ELECTRIC CITY
Funding Year 2013
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 1.86 mi.
ADT 200
Functional Class Local Access
Type of Work Resurfacing
Project Contact Jacqueline Perman
Contact Email electriccity@homenetnw.net
TIB Engineer Andrew Beagle
Last Payment Date 01/07/2013

Project Schedule

  Target Date Actual Date
Project Selection Date   11/18/2011
Delayed Project Date 07/01/2014  
Predesign Approval
Design Approval 01/01/2012 12/30/2011
Bid Auth. Approval 05/01/2012 12/30/2011
Construction Approval 08/01/2012 07/01/2012
Project Closeout 12/01/2012 01/03/2013
Audit Date   01/07/2013
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 50,302 14,219
Other Construction 0 46,891
Total Construction 50,302 61,110
     
Funding Increase 10,808  
Total TIB Funding 61,110 61,110

Local Funding Partners

Funding Amount Percent
ELECTRIC CITY 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The city will chip seal the following streets Sunset Drive - Electric to Silver, Kelso Avenue - Sunny to State, Kent Street - Kelso Palmer, Park Avenue - Stevens to McNett, Electric Blvd - Grant to Sunset, Stevens Avenue - Crest to Sunset. The city will fog seal the following streets Sunset Drive - Siver to Western, Stevens Avenue - Western to Crest, Hillcrest Avenue - SR 155 to Electric.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments