Town of Coulee City's FY 2012 Overlay Project
2-E-856(002)-1
2-E-856(002)-1
FY 2012 Overlay Project
Multiple Locations
FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $95,825
County: Grant | Legislative District: 12 | Project Length: 0.38 | TIB Engineer: Andrew Beagle | Last Payment Date: 09/28/2011
Project Information
Lead Agency | COULEE CITY |
Funding Year | 2012 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.38 mi. |
ADT | 200 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Alta Paulsson |
Contact Email | tcoulee@odessaoffice.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 09/28/2011 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2010 | |
Delayed Project Date | 07/01/2013 | |
Predesign Approval | ||
Design Approval | 12/15/2010 | 01/11/2011 |
Bid Auth. Approval | 06/01/2011 | 01/11/2011 |
Construction Approval | 07/01/2011 | 06/07/2011 |
Project Closeout | 09/30/2011 | 09/15/2011 |
Audit Date | 09/28/2011 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 13,260 |
Right of Way | 0 | 0 |
Total Design | 0 | 13,260 |
Construction Engineering | 0 | 6,573 |
Construction Contract | 99,948 | 68,135 |
Other Construction | 0 | 7,857 |
Total Construction | 99,948 | 82,565 |
Funding Increase | 4,820 | |
Funding Surplus | - 8,943 | |
Total TIB Funding | 95,825 | 95,825 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COULEE CITY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will prelevel and overlay McEntee Street between Main Street and Locust Street and Walnut Street between McEntee Street and 18 NE with a 2-inch overlay.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |