City of Republic's FY 2017 Overlay Project

2-E-855(002)-1

2-E-855(002)-1
FY 2017 Overlay Project

Multiple Locations

FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $154,594

County: Ferry   |   Legislative District: 7   |   Project Length: 0.29   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/14/2018

Project Information

Lead Agency REPUBLIC
Funding Year 2017
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 5
Federal Route Number 9999
Project Length 0.29 mi.
ADT 250
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Jennifer Rabenold
Contact Email cor@rcabletv.com
TIB Engineer Andrew Beagle
Last Payment Date 11/14/2018

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2015
Delayed Project Date 07/01/2018  
Predesign Approval
Design Approval 01/15/2016 04/21/2016
Bid Auth. Approval 12/15/2017 01/25/2018
Construction Approval 02/15/2018 03/22/2018
Project Closeout 12/31/2018 11/01/2018
Audit Date   11/14/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 12,192 11,993
Right of Way 0 0
Total Design 12,192 11,993
     
Construction Engineering 12,192 12,303
Construction Contract 128,011 130,298
Other Construction 0 0
Total Construction 140,203 142,601
     
Funding Increase 10,184  
Funding Surplus - 7,985  
Total TIB Funding 154,594 154,594

Local Funding Partners

Funding Amount Percent
REPUBLIC 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project provides crack seal, pavement repair and overlay to restore the surface on Kean Street. The consultant in coordination with TIB determined an adequate roadway section for Hesse. The scope includes placing crushed surfacing and overlaying the section. Minor drainage improvements ensure the street drains properly.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.