Severe deterioration exists on Hesse Boulevard from the Mobile Park Entrance to SR 20. Kean Street between 8th and 6th is ready for maintenance. Localized areas of alligator cracking are present on Kean Street near the bus barn.
Projects — TIB Project Information
TIB Project Information
City of Republic's FY 2017 Overlay Project
2-E-855(002)-1
2-E-855(002)-1
FY 2017 Overlay Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $154,594
County: Ferry | Legislative District: 7 | Project Length: 0.29 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/14/2018
Project Information
Lead Agency | REPUBLIC |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.29 mi. |
ADT | 250 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Jennifer Rabenold |
Contact Email | cor@rcabletv.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/14/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 04/21/2016 |
Bid Auth. Approval | 12/15/2017 | 01/25/2018 |
Construction Approval | 02/15/2018 | 03/22/2018 |
Project Closeout | 12/31/2018 | 11/01/2018 |
Audit Date | 11/14/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 12,192 | 11,993 |
Right of Way | 0 | 0 |
Total Design | 12,192 | 11,993 |
Construction Engineering | 12,192 | 12,303 |
Construction Contract | 128,011 | 130,298 |
Other Construction | 0 | 0 |
Total Construction | 140,203 | 142,601 |
Funding Increase | 10,184 | |
Funding Surplus | - 7,985 | |
Total TIB Funding | 154,594 | 154,594 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
REPUBLIC | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project provides crack seal, pavement repair and overlay to restore the surface on Kean Street. The consultant in coordination with TIB determined an adequate roadway section for Hesse. The scope includes placing crushed surfacing and overlaying the section. Minor drainage improvements ensure the street drains properly.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |