Projects — TIB Project Information
TIB Project Information
Town of Waterville's FY 2009 Overlay Project
2-E-854(002)-1
2-E-854(002)-1
FY 2009 Overlay Project
Ash Street
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $62,160
County: Douglas | Legislative District: 12 | Project Length: 0.49 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/05/2010
Project Information
Lead Agency | WATERVILLE |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.49 mi. |
ADT | 350 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Marsha Peterson |
Contact Email | waterville@nwi.net |
TIB Engineer | Andrew Beagle |
Last Payment Date | 01/05/2010 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 08/10/2008 | 08/21/2008 |
Bid Auth. Approval | 08/10/2008 | 08/21/2008 |
Construction Approval | 07/31/2009 | 08/03/2009 |
Project Closeout | 10/31/2009 | 12/31/2009 |
Audit Date | 01/05/2010 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 62,160 | 141,055 |
Other Construction | 0 | 0 |
Total Construction | 62,160 | 141,055 |
Total TIB Funding | 62,160 | 141,055 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WATERVILLE | 78,895 | 55.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 78,895 | 55.9% |
Project Description
This project consists of preleveling and a 2 inch overlay of Ash Street - Jackson to Chelan Greene Street - Locust to First Warren Street - Locust to Poplar Locust Street - Central to Warren Poplar Street - Columbia to Jackson
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |