Projects — TIB Project Information
TIB Project Information
Town of Mansfield's 2021 Chip Seal
2-E-852(007)-1
2-E-852(007)-1
2021 Chip Seal
Multiple Locations
FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $145,323
County: Douglas | Legislative District: 12 | Project Length: 0.82 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/03/2023
Project Information
Lead Agency | MANSFIELD |
Funding Year | 2023 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.82 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Tricia Sima |
Contact Email | mansfield@nwi.net |
TIB Engineer | Andrew Beagle |
Last Payment Date | 01/03/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
Predesign Approval | ||
Design Approval | 01/01/2022 | 04/07/2022 |
Bid Auth. Approval | 05/31/2022 | 06/15/2022 |
Construction Approval | 06/30/2022 | 06/15/2022 |
Project Closeout | 12/31/2022 | 12/16/2022 |
Audit Date | 01/03/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 140,340 | 0 |
Other Construction | 0 | 145,323 |
Total Construction | 140,340 | 145,323 |
Funding Increase | 4,983 | |
Total TIB Funding | 145,323 | 145,323 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MANSFIELD | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Work will include crack sealing, pavement repairs, preleveling work, and chip sealing.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |