Projects — TIB Project Information
TIB Project Information
Town of Mansfield's 2017 Emergency Pavement Repair Project
2-E-852(005)-1
2-E-852(005)-1
2017 Emergency Pavement Repair Project
Various Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $3,257
County: Douglas | Legislative District: 12 | Project Length: 0.10 | TIB Engineer: Andrew Beagle | Last Payment Date: 02/01/2018
Project Information
Lead Agency | MANSFIELD |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Jesse Shafer |
Contact Email | mansfield@nwi.net |
TIB Engineer | Andrew Beagle |
Last Payment Date | 02/01/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 06/02/2017 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 07/01/2017 | 06/27/2017 |
Bid Auth. Approval | 07/01/2017 | 06/27/2017 |
Construction Approval | 07/01/2017 | 06/27/2017 |
Project Closeout | 08/31/2017 | 01/24/2018 |
Audit Date | 02/01/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 1,089 | 3,257 |
Other Construction | 0 | 0 |
Total Construction | 1,089 | 3,257 |
Funding Increase | 2,168 | |
Total TIB Funding | 3,257 | 3,257 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MANSFIELD | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
See Approved Scope
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |