TIB Project Information

Town of Mansfield's FY 2012 Sidewalk Maintenance Project

2-E-852(003)-1

2-E-852(003)-1
FY 2012 Sidewalk Maintenance Project

Multiple Locations

FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $19,625

County: Douglas   |   Legislative District: 12   |   Project Length: 0.04   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 12/27/2011

Project Information

Lead Agency MANSFIELD
Funding Year 2012
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.04 mi.
ADT 150
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Tom Snell
Contact Email mansfield@nwi.net
TIB Engineer Andrew Beagle
Last Payment Date 12/27/2011

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2010
Delayed Project Date 07/01/2013  
Predesign Approval
Design Approval 12/15/2010 01/21/2011
Bid Auth. Approval 06/01/2011 01/21/2011
Construction Approval 09/21/2011 09/26/2011
Project Closeout 12/31/2011 12/27/2011
Audit Date   12/27/2011
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 500
Construction Contract 11,991 19,125
Other Construction 0 0
Total Construction 11,991 19,625
     
Funding Increase 7,634  
Total TIB Funding 19,625 19,625

Local Funding Partners

Funding Amount Percent
MANSFIELD 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

This project will repair damaged segments of sidewalk along Main Street between 1st Street and Railroad and two segments along Main Street between 1st Street and 2nd Street.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments