TIB Project Information

Town of Mansfield's Overlay Project

2-E-852(001)-1

2-E-852(001)-1
Overlay Project

Town of Mansfield

FY 2007 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $29,754

County: Douglas   |   Legislative District: 12   |   Project Length: 0.30   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 12/07/2006

Project Information

Lead Agency MANSFIELD
Funding Year 2007
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.30 mi.
ADT 150
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Tyler Caille
Contact Email mansfield@nwi.net
TIB Engineer Andrew Beagle
Last Payment Date 12/07/2006

Project Schedule

  Target Date Actual Date
Project Selection Date   01/27/2006
Delayed Project Date 07/01/2008  
Predesign Approval
Design Approval 01/27/2006
Bid Auth. Approval 01/27/2006 01/27/2006
Construction Approval 07/01/2006 08/01/2006
Project Closeout 10/31/2006 12/07/2006
Audit Date   12/07/2006
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 3,703
Construction Contract 74,426 18,194
Other Construction 0 7,857
Total Construction 74,426 29,754
     
Funding Surplus - 44,672  
Total TIB Funding 29,754 29,754

Local Funding Partners

Funding Amount Percent
MANSFIELD 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Small City Preservation Overlay Project Walnut Street - SR 172 to 2nd Street

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.