Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Funding Cycles

FY 2026 SCPP Selections

Town of Winthrop
2025 Chip Seal
Multiple Locations
TIB Award Amount
$481,815
Region: East   |   Legislative District: 7   |   Length: 0.00 mi. FY 2026 Small City Preservation Program (SCPP)

Existing Conditions

Anticipated Project Costs

  TIB Funds Local Funds Total Costs
Design 21,901 1,152 23,053
Right of Way 0 0 0
Construction 459,916 24,206 484,122
Project Totals $481,815 $25,360 $507,175

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 5%

Description of Improvements

Chip or Otta Seal.