Projects — TIB Funding Cycles
FY 2024 SCPP Selections
|
|
||||
| Region: East | Legislative District: 9 | Length: 0.00 mi. | FY 2024 Small City Preservation Program (SCPP) |
Project Information
| Agency Name | Town of Colton |
| Funding Year | FY 2024 |
| Program | SCPP |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | |
| Type of Work | |
| Project Contact | Jerry Weber |
| Contact Email | coltontownhall@hotmail.com |
Project Schedule
| Milestone | Target Date |
|---|---|
| 60% Review Date | 06/01/2023 |
| Start Design Engineering | |
| Contract Advertisement | |
| Contract Award | 07/01/2023 |
| Project Complete | 08/31/2023 |
![]() |
Existing Conditions |
Anticipated Project Costs
| TIB Funds | Local Funds | Total Costs | |
|---|---|---|---|
| Design | 0 | 0 | 0 |
| Right of Way | 0 | 0 | 0 |
| Construction | 127,725 | 0 | 127,725 |
| Project Totals | $127,725 | $0 | $127,725 |
Local Match
| TIB Participation | Local Match | Minimum Local Match |
|---|---|---|
| 100.0% | 0.0% | 0% |
Summary of Improvements
Description of Improvements
Chip Seal of the following segments: Lincoln Street - Summit St to End Vulcan Street - Gregor St to Union St Fountain Street - Lake St to Line St Harrison Street - Summit St to Gregor St College Street - Steptoe St to Summit St Line Court - College St to End Lake Street - College St to Harrison St