City of Leavenworth
2024 Street Maintenance
Multiple Locations
TIB Award Amount
$90,000
Region: East   |   Legislative District: 12   |   Length: 0.00 mi. FY 2025 Small City Maintenance Program (SCMP)

Existing Conditions

cracking, rutting and alligator distresses exist throughout the street network.

Project Funding

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 90,000 10,000 100,000
Project Totals $90,000 $10,000 $100,000

Local Match

TIB Participation Local Match Minimum Local Match
90.0% 10.0% 10%

Description of Improvements

A combination of crack sealing, completing spot pavement repair (grinding and repaving) and pre-leveling.