Projects — TIB Funding Cycles
FY 2021 SCAP Selections
|
|
||||
Region: East | Legislative District: 16 | Length: 0.19 mi. | FY 2021 Small City Arterial Program (SCAP) |
![]() |
Existing ConditionsCurrent configuration of Taggart Road includes a series of 90 degree corners and narrow road alignment deviations that makes traveling along Taggart road slow and dangerous. City has already completed the construction of the road base and intersection approaches and moved the corresponding utilities. Project need is to provide an asphalt top to the new road bed. |
Project Funding
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 3,849 | 1,151 | 5,000 |
Right of Way | 0 | 0 | 0 |
Construction | 131,651 | 39,349 | 171,000 |
Project Totals | $135,500 | $40,500 | $176,000 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
77.0% | 23.0% | 0% |
Summary of Improvements
- Improves safety
Description of Improvements
Project plan is to build an extension of the current Taggart Road back to US 12 as means to straighten out the road and improve traffic safety associated with current intersection of Taggart and US 12. Current solution is to provide an asphalt top to previoiusly constructed road bed.