Pacific Highway consists of two 11 to 12-feet travel lanes in each direction between Larsen Road and the existing sidewalk about 1,900 lineal feet south. There is no shoulder along the travel lanes. New development at the northwest edge of the city has added 250 new homes and 144-unit apartment complex. Travel from these new units to the schools or downtown La Center is only accessible by vehicular travel. Pedestrian or bicycle travel is not available along this section of highway.
Projects — TIB Project Information
TIB Project Information
City of La Center's Pacific Highway Shared Use Path
P-W-949(001)-1
P-W-949(001)-1
Pacific Highway Shared Use Path
Larsen Dr to existing sidewalk
FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $500,000
County: Clark | Legislative District: 20 | Project Length: 1,900.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | LA CENTER |
Funding Year | 2026 |
Program | ATP |
Current Phase | Design |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | D063 |
Project Length | 1900.00 mi. |
ADT | 2,065 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Tony Cooper |
Contact Email | acooper@ci.lacenter.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 12/15/2024 | 12/04/2024 |
Bid Auth. Approval | 02/01/2025 | |
Construction Approval | 05/01/2025 | |
Project Closeout | 10/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 500,000 | 3,480,000 |
Other Construction | 0 | 0 |
Total Construction | 500,000 | 3,480,000 |
Total TIB Funding | 500,000 | 3,480,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LA CENTER | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Transportation Alternative -fed | 700,000 | 20.1% |
State appropriation | 1,000,000 | 28.7% |
La Center | 1,280,000 | 36.8% |
Total Local Funding | 2,980,000 | 85.6% |
Project Description
A 10-feet wide shared use concrete path is currently being designed between Larsen Drive and the existing sidewalk adjacent to Kays Subdivision. This will be approximately a 1,900 lineal foot wide path, with a bridge installed over the existing creek adjacent to the guardrail. Retaining walls will be installed along the length of the trail to stay within existing city right of way. The path will be lighted with cobra head lights that will light the path and Pacific Highway.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |