US 101 is the primary route between the City of Aberdeen and the City of Cosmopolis, but this section of the corridor has gaps in the existing sidewalk, has many non-ADA compliant curb ramps, and lacks bicycle facilities requiring bicyclists to travel in the lanes of US 101.
Projects — TIB Project Information
TIB Project Information
City of Aberdeen's US 101 Safety Improvements
P-W-189(P04)-1
P-W-189(P04)-1
US 101 Safety Improvements
US 101 from the City of Cosmopolis MP 81.73 to the Chehalis River Bridge MP 83.17
FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $438,330
County: Grays Harbor | Legislative District: 19 | Project Length: 2,350.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | ABERDEEN |
| Funding Year | 2025 |
| Program | ATP |
| Current Phase | Construction |
| Legislative District | 19 |
| Congressional District | 6 |
| Federal Route Number | 0101 |
| Project Length | 2350.00 mi. |
| ADT | 9,400 |
| Functional Class | Principal |
| Type of Work | Pedestrian |
| Project Contact | Kyle Fisher |
| Contact Email | kfisher@aberdeenwa.gov |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 01/01/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2024 | 12/20/2023 |
| Bid Auth. Approval | 10/30/2025 | 10/21/2025 |
| Construction Approval | 02/01/2026 | 01/28/2026 |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 58,776 | 202,500 |
| Construction Contract | 391,224 | 1,998,318 |
| Other Construction | 0 | 0 |
| Total Construction | 450,000 | 2,200,818 |
| Funding Surplus | - 11,670 | |
| Total TIB Funding | 438,330 | 2,200,818 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ABERDEEN | 97,488 | 4.4% |
| WSDOT Funding | 765,000 | 34.8% |
| STP | 900,000 | 40.9% |
| Total Local Funding | 1,762,488 | 80.1% |
Project Description
Preliminary studies have demonstrated that a 3-lane section will accommodate anticipated growth and that a road diet is warranted. The existing 4-lane section will be converted to a 3-lane section to provide dedicated bike lanes.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers;
- Builds multimodal facilities
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||